How long does an extension take in Kent? Real programmes, not wishful ones

Homeowners hear 'eight weeks' and assume keys back by half-term. Sometimes that is fair. Often the clock starts later than people think. Here is a Medway builder's view of the full timeline.

Get a Free Estimate

Before anyone digs

Design, planning or lawful development, party wall, structural calcs, building control notice and lead times on windows and kitchens — that pre-construction block can take months.

A smooth single-storey with clear PD and a cooperative neighbour still needs drawings and materials lined up. Rushing this stage is how rainy site weeks turn into arguments.

Typical time on site

Many quality single-storey extensions in Medway land around 8–14 weeks on site once we start. Wraparounds, two-storey and heavy steel schemes take longer. Kitchen manufacturing can add a waiting gap if ordered late.

Weather matters. Foundations and roofing hate prolonged wet spells. We build float into programmes rather than promising miracle dates.

  • Compact rear single-storey: often 8–12 weeks
  • Kitchen-diner with glazing: often 10–16 weeks
  • Two-storey: commonly longer
  • Loft conversion: often 6–10 weeks on site

What slows jobs down

Late client decisions on tiles and kitchens, unforeseen ground conditions, slow party wall responses and supplier delays. Clear early choices from you help as much as good project management from us.

Napwood keeps you updated week to week so surprises are rare. Ask any builder for a written programme and what assumptions sit under it.

FAQs

Frequently asked questions

Can you finish before Christmas / a birthday?

Sometimes, if we start early enough and decisions are locked. Fixed celebration dates need an honest look at the calendar — we will not promise what the programme cannot carry.

Does living on site make it slower?

It can, because we protect living areas and work around you. Vacating speeds some stages but is not always practical.

When does the 8–14 weeks start?

On site start — after permissions, steels ordered and the enabling works are ready. Not from the first cup of tea on the sofa.

How do I get a programme for my house?

Book a consultation. Once we understand scope, we outline pre-construction and on-site stages in plain English.

Ready to discuss your project? Call us or request a free estimate today.